Update @ Parshuramdwara School 20 Sep 07

Tr. Tarun, Tr. Shishir and myself had gone to the Parshuramdwara School project site on the 20 September. The school bulding progress is ok and on track. Some points to note:
  • The Ground Floor is in its finishing touches, 1 classroom has got 1 blackboard ready, but the flooring will still take about a week to be finished.
  • The Firts Floor still has about 2 weeks of work due.
  • The electrical wiring is yet to be put in.
  • On suggestion of the school headmaster, the contractor has put steel sheets instead of glass in the windows. outside is a steel-Jaali and inside is now steel sheets.
  • We will be able to start whitewash by 1 week of Oct, once the flooring is complete.

We are on track for the inauguration of the school on our 5th birthday ie., by 20th October.

Tr. Manish Kasliwal,
JPRT Ka Munshi