Update 6th June
9:15 am: Tr. Ashish, Tr. Chinmay, Tr. Pushpendra and Tr. Manish visited the School...
The work-in-progress is as per schedule and the structure till 4 feet of the plinth is complete. The pillars have been cast up to 6 feet and once the centre corridor plinth is filled and the full pillar work is finished by end of this week, we will start work on the roof (hopefully) by end of next week...
The work-in-progress is as per schedule and the structure till 4 feet of the plinth is complete. The pillars have been cast up to 6 feet and once the centre corridor plinth is filled and the full pillar work is finished by end of this week, we will start work on the roof (hopefully) by end of next week...
The issue of overhead power lines has yet to be resolved. The GM has sent a letter to RSEB but nothing has moved as yet... any more delay in this and we will be put on hold... so we need to solve this issue asap.
'Kudos' to Tr. Ashish for giving a cheque of Rs 70,000 as the donations he has collected.
Boys, we need to get more money in and NOW, we already are looking at 6 lacks rupees cost over run...
Hoping to see more money by next Update,
Will keep you posted...
Aapka Manishva...